Secret terminal block production processes
2017-11-20

Terminals production can be divided into three steps: stamping, injection molding and final assembly and packaging. To specifically talk about the three following processes.


First,stamping production process


Sheet metal to the plant - sheet metal sub-- collar stamping - process checks - tool maintenance - electroplating - metal terminal


Second,injection molding production processes


Plastic expect plants - the material is dry - injection molding production - process inspection - Molded Case


Third,assembly and packaging process


The above-mentioned materials and parts of the collar Qi - raw materials and parts assembly - Tighten the screws - process checks - Product packaging - shipping / storage check the terminal block production three processes, although simple, but in the process of production or the need for all aspects of account, security The production is first.